| Milestone |
WP no. |
Lead |
Initial delivery date |
Initial delivery month |
Updated delivery date |
Updated delivery month |
| No. |
Name |
| M1 |
Electronic tools operational to support all WPs |
WP1 - Task 1.3 |
IFIN-HH |
m6 |
Aug. 2008 |
m12 |
Feb. 2009 |
| M2 |
Census of funding programmes delivered |
WP2 - Task 2.2 |
PTGSI |
m12 |
Feb. 2009 |
m16 |
June 2009 |
| M3 |
General approval of the Funding Plan for joint activities for Europe |
WP3 - Task 3.3 |
CEA |
m24 |
Feb. 2010 |
m27 |
May 2010 |
| M4 |
Selection of one or more joint transnational activities |
WP4 - Task 4.2 |
FECYT |
m27 |
May 2010 |
m30 |
Aug. 2010 |
| M5 |
Launch of a pilot transnational activity |
WP4 - Task 4.3 |
FECYT |
m33 |
Nov. 2010 |
unchanged |
| M6 |
Creation of the "preparatory group" for the future managing of European joint activities in nuclear physics infrastructures |
WP4 - Task 4.4 |
NKTH |
m35 |
Jan. 2011 |
unchanged |